ASRANet

Network for Integrating Structural Analysis, Risk and Reliability

 Public access

Introduction

Structure

Working Groups

Join ASRANet online

ASRANet courses and events

Links

Newslettters

Products

What's New

Contact us

Search the site

 Members' Pages

Groups

Colloquium 2000 papers

Research priorities and opportunities

What's new for members

List of Members' links

 

Bridges in the News

Forth Road Bridge

The Forth Road bridge is expected to get top Listed Building status if Historic Scotland approve a report under consideration. See Structurae's site for pictures of bridge, including during construction, and access to their database of worldwide structures old and new.

Analysing the structural dynamics of extreme bridges
by Dave Parker 10/08/2000, examples extracted from
NCE+ which also has a huge "Knowledge bank" of articles on cutting-edge bridge design techniques and projects

 Java-Bali Bridge   Fink rethink  Kingston Bridge, Glasgow  Millennium Bridge
     

 As bridges become more extreme, the limiting factor is no longer the strength or durability of the materials used. Dynamic response to wind, earthquakes and traffic loads dominate the design process. Dave Parker reports on how designers have dealt with dynamic challenges on three extreme bridges. Record breaker Spanning 2.3km across the typhoon haunted waters of the Bali Sea, the Java-Bali Bridge will be the longest in the world – if it opens before the giant Messina crossing.

There is still no certainty the landmark structure will ever be built, but the concept design has posed some interesting challenges for structural engineer Flint & Neill, not least on the dynamic front. Flint & Neill partner Ian Firth explains: “We chose a hybrid cable stay/suspension bridge design because this effectively reduces the suspended span to 1,600m. And
the cable stayed backspans with their multiple piers are very stiff. So the natural frequencies of the deck are higher, amplitudes of motion are lower and it responds much better to wind loads.” Given the high probability of typhoons in the area the aerodynamic characteristics of the structure were crucial. Deck design was made no easier by the client’s decision that only two traffic lanes in each direction were needed.A conventional single deck girder would have been unfeasibly narrow for the record-breaking span. To achieve the necessary lateral stiffness Flint & Neill went for a cross-braced twin box design, with a 16m central slot between the aerofoil cross-section steel boxes. “Messina style slotted decks are very efficient aerodynamically,” Firth points out. “And the separation helped us develop a very efficient tower design with a distinctly Balinese flavour.” Unusual they may be, but Firth insists the 300m high towers have much greater transverse stiffness than conventional portal frame designs. He also expects that once detail design begins the real challenge will be fine tuning the cross sections of each box in the wind tunnel. “Vortex shedding is the key issue – predicting how curved soffit box girders will behave is really difficult.” Aerolastic testing –modelling the dynamic response of the structure to high winds – will also include the effect of local topology, Firth adds. Lateral and torsional motion on long span structures is a problem for which Firth sees no simple solutions. Active damping and “intelligent” aerodynamic control fail to impress. He sees the risk of power or equipment failure as too high. But passive aerodynamic damping – “flat plates paddling air” – is another matter. Such appendages would make Java-Bali an even more dramatic crossing.

Had it been built with active damping, the Royal Victoria Dock footbridge in London’s Docklands would have weighed 25% less. So says structural engineer Tekniker director Matthew Wells,adding: “The original intention was to react to deflections caused by the passenger gondola which will eventually run below the deck. “The system could in theory have coped with all imposed loads – the problem was defining which frequencies to damp.”

A mini transporter bridge design was architect Lifschutz Davidson’s response to a design brief from the then London Docklands Development Corporation for a landmark 130m span pedestrian crossing over a stretch of water which was being
developed as a regional sailing centre. A 13m minimum clearance below the deck seemed to imply that pedestrians would need some form of weather protection – but at the same time the structure had to cause as little wind turbulence as possible. “Some form of tube would have been a possibility,” says Wells. “But who would want to cross it late on Saturday night?” The transporter bridge alternative would allow pedestrians to enjoy the views from the open top deck in fine weather, with the option of skimming across the dock in a 40 passenger enclosed car in less clement conditions.

An inverted Fink truss was the chosen structural form, partly because of its inherent lightness and flexibility, partly because it invoked both the dockyard cranes and the forest of masts and cables that once filled the dock.Five fabricated “whale backbone” steel box girders linking the six masts were spigoted together around the mast feet. This simple to erect pin-jointed arrangement also significantly increased the structure’s inherent lateral damping.Beneath this backbone runs the track for the passenger gondola, which weighs 11t fully loaded. Wells says the gondola only increases midspan deflection by a maximum of 75mm. “Dynamically, there was no problem with the gondola swinging beneath the deck, as its ‘bouncing’ frequency is very much lower than that of the bridge.And in high winds it will be able to winch itself close up under the deck during the crossing.” Doubts about development time for an actively damped solution meant Techniker went for a “static” solution at competition stage. As design development began, tests revealed a potential aerodynamic problem – the first torsional and first vertical frequencies were very close together, less than 0.5Hz apart. “Normally you would expect vertical to be around 1Hz with torsional three or four times higher,” Wells comments. “When they’re this close you could be facing a Tacoma Narrows
situation.”

Aerodynamic damping via a perforated balustrade proved to be the solution to this particular problem. Meanwhile, Techniker worked up two alternative active damping designs, using adapted Formula One self-levelling suspension technology applied to the backstays This promised a massive weight reduction and a cut in the maximum depth of the box girders from 1,650mm to 1,250mm. There was a downside, however. Wells explains: “With full active damping it would be impossible to use the bridge in high winds if there was any equipment failure. Then there was the ongoing cost of maintenance. But the real problem was the time needed to decide on the sampling
window – which motions to monitor and to correct.”

 Between midnight and 5 am on 05/08/00 the bridge was lowered 10mm and moved southwards 10mm. There will be another 24 hour closure on 12/08/00 for bearings to be jacked into place and a final closure on 26-27/08/00 to put the bridge onto the bearings.

Lifting jacks have supported the bridge for seven months while new concrete piers have been constructed. The bridge , built in 1970, is one of Europe's busiest, carrying an average 150,000 vehicles a day - five times original estimates. . The £31.5m operation began after the discovery of major defects in the bridge in 1990. The north pier wall near the bridge's support piers was found to be bulging.


Extract from the Scotsman newspaper (31/07/00):

MSP calls for fresh assessment of Kingston Bridge , Andrew Murray-Watson


A GLASGOW MSP has called for an independent assessment of the Kingston Bridge after concerns that it will not be able to cope with ever-increasing levels of traffic. Strengthening work, being undertaken has so far cost £33 million. Despite assurances from the Scottish executive, the SNP’s local government spokesman, Kenny Gibson MSP, wants independent checks made on the bridge to guarantee its long-term future. Mr Gibson said: "Having spoken to several civil engineers, I am worried about the executive’s apparent confidence in the remedial work being carried out on the bridge.

"The experts I have consulted say that there is no guarantee that the work will restore the bridge to a condition one would expect it to be in after 30 years of life. However, the fact that there were severe structural design problems in the first place means that its rate of deterioration in the future is likely to be faster than accounted for, particularly given the fact that it was built to handle only a fraction of the traffic now using it."

The bridge is due to be closed on four separate occasions. On Saturday (05/07/00) evening all traffic will be diverted for 24 hours while the bridge is lowered in order for essential work to be completed. Mr Gibson added: "Sarah Boyack, the minister responsible, can happily say that she expects the bridge to live out the balance of its engineering life, because all they have are estimates, they don’t actually know for certain. I will therefore be asking the executive if they intend to keep publishing the results of the structural monitoring of the bridge after the current work is finished. If yes, then fine. If not, then they obviously have something to hide."

An Executive spokesman said that the bridge had a long future: "Strengthening work and normal maintenance will mean that the bridge will be able to see out its 120 year life-span -even given the additional traffic."

 Bad vibrations

Update: Aug 2000:

Arup's investigation results will be available in August, with remedial work starting in September, possibly overseen by the City of London's engineers. The bridge will remain closed to the public.

Extract from New Scientist 08 July 2000.

How could the designers of a revolutionary bridge miss something so obvious?

Engineers who designed London's wobbly Millennium Bridge admitted last week that the computer simulations they used to model its behaviour couldn't cope with the effect of people walking across it. The blunder, say observers, resulted from an out-of-date standard for testing bridges and poor dissemination of information in the industry about previous incidents.

The 320-metre footbridge over the Thames, which cost £18 million, was closed on its opening weekend last month, when it was found to wobble more than expected. Since then Arup, the engineering firm responsible for the bridge, has been analysing its response to vibrations.

The engineers used shaking machines to send vibrations through the bridge. They found that horizontal vibrations at 1 hertz (one complete cycle per second) sent the bridge into the kind of S-shaped lateral wobble that was seen when it opened.

This was a clue to the source of the problem, says Pat Dallard of Arup, structural adviser on the bridge project. "Normal walking pace is about two strides a second, so you produce a vertical force at around 2 hertz," he says. But the horizontal frequency is half that. "As we walk, one foot pushes left, then the other pushes right, so you have a 1-hertz horizontal force," he says.

Ian Sample

 Disclaimer: Nothing that appears in any part of ASRANet's website implies any endorsement of software or other services mentioned in the site. Users are reccommended to take the normal precautions before using information, software or any other services.

Last updated:11/08/04

Author: ASRANET Secretariat